Finance November 2022 Update

What We Are Working On Configuration Tenant Build In October, the cumulative results from Future-State Process Design (FSPD) Playback sessions and input from Focus, Validation, and Governance Groups were loaded into the latest UW-specific Workday …

IT November 2022 Update

As we prepare for the Configure & Prototype (C&P) Stage, the IT Strategy Team continues to increase its understanding of Workday and the associated technology needs. After careful review and consideration of resources, a plan …

HR November 2022 Update

Workday Progress and Updates  FSPD Completion The final step in the Future State Process Design (FSPD) process is to sign off on technical documents, which include details of the work done currently for the end-to-end …

HR October 2022 Update

Workday Progress and Updates  Configuration Workbooks The HR Design Teams have incorporated feedback from Future State Process Design (FSPD) Playback sessions and guidance from Focus, Validation, and Governance Groups to complete configuration workbooks for each …

Research Admin October 2022 Update

Workday The Research Admin Strategy Team continues to make great progress in the Architect Stage of the Workday implementation. In September, the team continued to work through the design of many individual processes. (For a …

Finance October 2022 Update

ATP’s Finance Team has completed five months of the Architect (Design) Stage, which will end on November 30. Thanks to our engaged campus stakeholders, the majority of our design decisions have been made by this …

IT October 2022 Update

The IT Strategy Team continues to increase its understanding of Workday and the associated technology needs as we complete Architect Stage–related activities and prepare for the Configure & Prototype Stage. As we move through the …